North Dakota Renewable Diesel Project
C2C Technical Services was selected as the primary electrical and instrumentation contractor to assist in the conversion of a major petroleum refinery into a renewable diesel facility. Our customer trusted us to fully staff and complete this 18-month project from start to commissioning with zero recordable incidents or injuries.
Numbers:
Spend: $25.5MM
Peak Headcount: 158
Man-hours Worked 233,000
Safety: 0 Recordable Incidents or Injuries
Scope:
- Commissioning of a new Honeywell Experion DCS system
- Installation and commissioning of over 6,000 loops
- All new LED lighting
- All new electrical heat trace and controllers
- Installation of electrical infrastructure for new electrical loads